The office fit-out programme, week by week

Related projects
All projectsAn office fit-out is counted in weeks, not vague months. This is the sequence we actually run: briefing and survey, concept design, tendering, permits, construction, handover. Allow 14 to 18 weeks for 600 sqm in refurbishment, and 6 to 10 weeks for 300 sqm of light works. Furniture and permits are the two items that make programmes slip.
Weeks 0 to 2 · briefing and survey
Site visit, dimensional survey, inventory of existing building services, interviews with the teams. The goal: fix desk numbers, areas per function and the target budget. This is the cheapest phase and the one that prevents the most errors.
Weeks 2 to 5 · concept design and costing
Layout drawings, material selection, services principles, cost per sqm. Two rounds with the steering group. By the end, 80% of the budget is committed: this is when to validate or correct, not later.
Weeks 5 to 8 · tendering and award
Consulting the trades, comparative analysis, contract finalisation. Allow two to three weeks. In design and build this phase sits inside our single contract.
Weeks 8 to 10 · permits and orders
Planning permission if the facade or structure changes, landlord approval, safety file. Place furniture orders now: twelve weeks is common for bespoke items.
Weeks 10 to 16 · construction and handover
Demolition, partitions, electrics, HVAC, floors, painting, furniture, finishes. Six weeks for 600 sqm in an occupied building, four for an empty floor. Always allow a buffer week.
Frequently asked questions
Frequently asked questions
- How long does an office fit-out take?
- Six to ten weeks for 300 sqm of light refurbishment, fourteen to eighteen weeks for 600 sqm, and four to six months for 1,000 sqm and above.
- When should furniture be ordered?
- As soon as the concept design is complete, eight to ten weeks before site completion. Bespoke furniture takes twelve weeks.
Let us talk about your project.
Tell us your floor area, your deadline and your constraints: we come back within 24 working hours with a first estimate and a site visit proposal.